Bottle customization process

25 Apr.,2021

glass bottle customize process

 

Custom glass bottle process


1. Create technical drawing of the requested bottle shape (1-2 days) Or clients provide the drawing, VCG analyze the technical feasibility and adjust if necessary. (1-2 days) (Provide the label artwork for technical analysis if needed)

2. Make 2D/3D drawing for clients’ approval (1 day)

3. Open sample mould / 1 set (15-20 days)

4. Produce clear bottle samples for clients’ approval (5-7 days)
 (Make decorated samples if needed /15 days )

5. Order confirmed, finish mass production moulds / 5 sets (20 days)

6. Clear bottle production (production time depends on the quantity)

7. Quality checking and assurance

8. Do paperless label printing if needed (QC & QA again)

9. Packing for shipment

10.Shipment

customization bottle process.png