Adoption of Modular Cooling Tower Technology

03 Jul.,2023

 

New modular cooling tower configurations are worthy of serious consideration for commercial HVAC as well as industrial applications. These large, efficient structures can nearly triple cooling capacity compared to typical single-cell, factory-assembled cooling towers, while using substantially less fan power to drive energy savings. Both crossflow and counterflow tower designs achieve a low measurable drift rate – down to 0.0005 percent of circulating water flow, and minimize piping and electrical connections. The entire installation process is shortened dramatically because delivery lead times are 60 percent shorter and field assembly is completed 80 percent faster compared with field-erected towers.

An example of new modularization technology is the Marley® NC Everest® Cooling Tower. It provides up to 50 percent more cooling capacity per cell and uses up to 35 percent less fan power per ton of cooling compared with other factory-assembled crossflow single-cell towers. The crossflow configuration offers several advantages, including easier access to the tower interior and mechanical components. It also permits “variable flow” operation, which reduces water flow rates and energy consumption during cooler weather. Its increased cooling capacity means fewer cells are required. Simpler installation reduces both construction and maintenance costs for HVAC and process cooling applications alike.

Another advanced modular design is the counterflow Marley MD Everest® Cooling Tower. With a flow rate up to 12,602 gallons per minute (GPM) per cell (2862 m3/hour), it offers nearly three times more cooling capacity per cell than typical preassembled counterflow towers. At 3790 nominal tons (12,300 kW) of cooling in a single cell, it is an excellent one-to-one match for larger HVAC chiller systems. Its unmatched capacity and robust materials of construction also make it a strong contender for process cooling assignments.

Modular cooling towers can be operational in just a few days, up to a week or two at most – which is about 10-20 percent of the time it takes to build a field-erected tower. Construction techniques are performed at ground level and fewer workers on-site reduce safety concerns. Modularization simplifies field assembly and operation, with fewer components to install and maintain.

Modular tower componentry is built in a controlled factory environment for consistently high quality and with predictable, shorter lead times from order to product delivery. For example, the Everest series tower modules can be built in as little as six to eight weeks, which is about one-third to one-half of the lead time necessary to deliver field-erected tower components.

Additionally, on-site performance testing of field-erected towers is often required to verify they meet the specified cooling capacity. The tests, conducted by independent third-party agencies, add costs of about $25,000. Because these new modular towers are certified by the Cooling Technology Institute (CTI) to meet thermal performance as specified, additional testing costs are eliminated.

A recent construction estimate to replace a field-erected cooling tower in the southeast United States required 4,500 hours and seven weeks of field labor. By specifying the modular NC Everest instead, installation duration contracted to less than two weeks – an enormous savings in time, expense and operational efficiency.

At a new data center project in upstate New York, two NC Everest tower cells providing nearly 5,000 tons of cooling were installed in one day, which was crucial to the operators who had strict security requirements and highly restricted access to the site.

In the Midwest, an oil and gas refiner needed to replace or rebuild a field-erected tower within a 19-day outage. Because it would have taken eight to 10 weeks to reconstruct the cooling tower, and longer to build from the ground up, the modular MD Everest tower was selected, allowing completion within the outage window. The customer also benefited from the smaller work crew required, which reduced logistical complexity and safety risk on-site.

Previously, field-erected cooling towers were the only solution available to meet the capacity demands of process cooling and large HVAC projects. Now, energy managers charged with evaluating cooling systems must also consider the advantages modular cooling tower systems offer in a broad range of applications. Greater cooling capacity with energy efficiency, faster delivery, shorter construction duration, fewer logistical requirements and safer assembly techniques all contribute to the value these highly-engineered modular cooling products offer to engineers, contractors and owners. Robust construction materials, counterflow and crossflow configurations, easier inspection and maintenance access, and performance testing and certification give tower operators the justification and confidence needed to move away from traditional field-erected products and embrace advanced modular cooling tower systems.

 

If you have any questions on cooling tower supplier. We will give the professional answers to your questions.